Synopsis:
This course is designed to introduce delegates to Contractors entitlement
for claims under the 6th edition of the ICE Conditions of Contract and
how that entitlement should be established and resolved to the satisfaction
of all concerned. The course will also afford time to review how claims
may be avoided and will include reference to relevant legal cases. The
purpose of this training course therefore is to study in detail the procedure
for recognition, presentation, examination and prompt settlement of bona
fide claims.
Course Duration:
One Day 0900 - 1700hrs
Course Level:
The course is intended for Quantity Surveyors, Commercial Managers
and those involved in Project Management.
Elements of the following training objectives are covered by the course:
CM2
CPD Approval:
Recommended 6 Hours CPD.
Objectives:
Appreciate the circumstances which give rise to claims
Understand the duties and responsibilities of the
Contractor and the Engineer
Recognise the procedures to be followed
Understand the evaluation process
Appreciate the value of negotiation
Have an insight to claims avoidance
Understand the major differences between the 5th, 6th and 7th
editions relating to the Contractors entitlement
Outline Programme:
Definitions and categories of claims
Basis for claims
Preparation and presentation of claims
Evaluating claims
Settlement of claims
Avoiding claims
Course Availability and Cost: